Quote

From:

721 Amsterdam St.
Woodstock, IL 60098
P.(847) 450 7850

ServiceFirstUSA@gmail.com
24/7 Dispatch: +1 (866)922 2580

Quote Number QUO-7496
Quote Date May 10, 2023
Total $34,500.00
To:
From the Ground Up Construction

Dear From the Ground Up Construction,

We, at this moment, propose to provide materials and labor to complete the HVAC job at 5947 N East Circle, Chicago, IL 60631, with a scope of work as follows:

First Floor and Basement:

  • Remove existing boiler system, piping, and radiators.
  • Install a 100k BTU Bosch high-efficiency furnace with a 5-ton Guardian AC system.
  • Install duct distribution in the basement to provide air to the first floor and basement.
  • All first-floor registers to be located on the floor, and all basement supply registers are to be found on the basement ceiling.
  • One high and low main return on the first floor
  • Installation of a 4" media filter
  • Installation of a Honeywell Wi-Fi-enabled Vision Pro programmable thermostat.

Second Floor:

  • Provide a 75k BTU Bosch high-efficiency furnace paired with a 3.5-ton Guardian AC system with horizontal installation
  • Ductwork distribution is to be located in the attic, with the supply registers to feed the second floor from the ceiling
  • One high and low main return in a common area
  • All bedrooms with one supply in each room
  • Installation of a 4" media filter
  • Installation of a Honeywell Wi-Fi-enabled Vision Pro programmable thermostat

Bathroom Exhaust:

  • Provide and install first and second-floor bathroom exhaust fans, vented to the exterior of the home

Job Exclusions:

  • Plumbing, electrical, drywall demolition and patching, job permits, and fees

Time Schedule:

  • The estimated project completion time is four weeks from the start date.

Disclaimer:

  • Service First USA is not responsible for any delays caused by other trades or circumstances out of our control.

Job Total: $34500.00

Payment Schedule:

  • 50% down payment
  • 25% when the first floor is completed
  • 25% when the job is done

Notes:

  • Additional work and changes will be done at an extra cost.

Thank you for considering Service First USA for your project. If you have any questions or concerns, please don't hesitate to contact us.

Hrs/Qty Service Rate/PriceAdjustSub Total
1 New Installation $34,500.000.00%$34,500.00
Sub Total $34,500.00
Tax $0.00
Total $34,500.00

2 comments

  1. Hi, every time i used to check blog posts here early in the
    morning, as i love to find out more and more.

  2. Great article and straight to the point. I don’t know if this is actually the best place to
    ask but do you folks have any ideea where to get some professional writers?
    Thank you 🙂 Escape roomy lista

Add a comment

Your email address will not be published. Required fields are marked *